Updates on Alice's Road Project

alices road const web

The Alice’s Road widening project continues as crews work to install storm sewer pipe and water main. Work to pour retaining walls and the pedestrian box culvert for the Heart of the Warrior Trail underpass portion of the project has begun; the trail is closed through project duration. Roadway embankment construction on the east side of Alice’s Road will begin soon. Once in place, paving of the eastern three lanes will follow. Subscribe to project updates.